Infrastructure upgrades  |  17 Mar 2025

Work to address issues with resurfacing work on Halswell Junction Road will begin at the end of the month.

This programme of work is the final phase of maintenance resurfacing, as well as remedial work on recently completed sections to create a more level and smoother surface.

“We’ve scheduled this remedial work to occur at the same time as the final phase of the work to help minimise the period of disruption to residents and road users,” says Christchurch City Council Manager City Streets Maintenance, Steve Guy.

“Both programmes of work will take place between 27 March and 9 April, Monday to Saturday, with traffic able to flow as usual before 9am and then restricted to one-way northbound only from 9am to 7pm.”

The road has not held up in several areas following the resurfacing works completed in early 2025, which has resulted in bumps and slumping.

Uneven surfaces can cause vibrations to homes when traffic passes. 

“We accept this has been very unpleasant for residents. We’re committed to delivering a surface that meets our quality standards and – with the use of asphalt rather than chipseal – is as smooth as possible. This will eliminate the road surface as a contributing factor to any pre-existing vibrations,” Mr Guy says. 

The final phase of work will see a waterproof seal applied at the Wigram Road and Whincops Road roundabout and the Hamill Road and Alvaston Drive roundabout, to improve durability and reduce the risk of potholes.

Work will progress north along Halswell Junction Road in stages, from just south of Nicholls Road to just south of the Southern Motorway, with detours in place for southbound traffic.

“We understand this work is disruptive for residents and traffic, and we appreciate everyone’s continued patience as we get this resurfacing work completed,” Mr Guy says. 

The maintenance resurfacing on Halswell Junction Road is a separate project to the Halswell Junction Road extension, which is located north of the motorway and is expected to open in mid-2025.

Find more details about the Halswell Junction Road resurfacing work on the Council website.